Day 4 More Destruction

 I thought we were past the deconstruction stage but I was wrong.  The electrician, plumber, and HVAC folx can work more efficiently if we just rip out the wall. 



We're going to upgrade and replace the insulation on this outside wall.  And as long as we're poking around, we're also going to stuff some more insulation into the roofline.

We also have our first unexpected finding and slight change in plan.


The ceiling behind the wall has partially collapsed.  The duct work for the exhaust fan is going to be re-routed through the ceiling so we will just re-enforce and secure this collapsed ceiling at the same time as we cut a new hole for the exhaust.  The contractor was expecting to climb around in our attic to install the exhaust duct work. We changed that plan because it will be easier to just work from the interior of the house to access the attic.  We have a low pitch roof and there is little, if any, space to crawl around the attic. 



In other news I managed to make a pasta dish using an induction hot-plate and a large pot. It was nice to eat a home-cooked meal.



Comments

  1. Looks delish!!! Drop the recipe so we can all enjoy a home-cooked meal!

    ReplyDelete

Post a Comment

Popular posts from this blog

Kitchen Remodel: Day 0 (Before Pictures)

Why remodel?  I first saw my current home in the Summer of 1999. The house was custom built in 1960 by an architect who made it his family's home.  We knew we wanted our new home to be  located close to my husband's new job (he could walk to his office)  be close to schools (elementary school is across the street) be welcoming to our aging parents who we hoped would visit often (it's a ranch style with gentle stairs to the basement) be close to a bus line to get to campus (8 minutes to walk to the bus stop). This house met all those requirements but the kitchen was dated and needed updating.  We made an offer, it was accepted, and we moved into the home in August of 1999. A short twenty-five years later we hired professionals to gut and re-build our kitchen. Our primary goals are to update our cooktop and oven, gain more counter space, gain more storage space, and get better lighting.  Here is a picture of our galley-style kitchen unchanged since we moved i...

All done!

 We officially finished on April 10th for a total of 95 days from project start to finish. We've been adjusting to the new layout and now have almost two-months of working in our new kitchen. I absolutely love it!  We achieved all of our goals with an updated cooktop, updated oven, more counter and storage space, and so much lighting. I was much more invested in the functioning of the new space rather than the aesthetics. However, when I saw how lovely everything turned out, I was briefly motivated to prioritize the neat clean look by keeping the counters clear and the fridge door free of clutter. Eventually I came to my senses and remembered that my kitchen is meant to be used and not only admired. Enjoy these final photos and be sure to look back to Day 0 for the before pictures. Some organizational hacks, some planned ahead of time, some not.

Days 2 & 3 More Destruction

  Yesterday they removed the soffits and today they removed the original 1960 linoleum flooring.  We knew that there was asbestos (25% Chrysotile) in the flooring.  Rather than adding another layer of flooring over the existing we decided to take out the old stuff.  Given the amount of safety equipment for the removal in 2025, I'm wondering how the workers who installed our floor and many others in 1960 fared.    I think the deconstruction is done and building can commence.